Temporary Electrical Power Outage (8/6~7, 8/27)

For regular inspections of electric installations as well as examinations and repairs on decrepit facilities, there will be a temporary electrical power outage as follows.

1. Grounds for the Power Outage:

A regular inspection and safety check by Korea Electricity Safety Corporation

2. Date, Time and Range of Power Outage:
  • A.1st Power Outage (the First Power Plant): Saturday, August 6th, 2011. 08:00~12:00(4 hr.)
  • B.2nd Power Outage (the Second Power Plant): Sunday, August 7th, 2011. 08:00~12:00(4 hr.)
  • C.3rd Power Outage (the Third Power Plant): Saturday, August 27th, 2011. 07:00~13:00(6 hr.)
Date, Time and Range of Power Outage
Date and Time Range(Building No,) Reasons for Power Outage
The First Power Plant Saturday, August 6th 08:00~12:00(4hr.) 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 10-1, 11, 12, 13, 14, 15, 16, 16-1, 17, 20, 21, 21-1, 22, 23, 24, 25, 26, 27, 28, 29, 34, 36, 43, 46, 56, 60, 61, 62, 63, 64, 65, 65-1, 66, 67, 68, 68-2, 71, 71-1, 71-2, 72, 73, 76, 76-1, 80, 80-1, 83, 84, 85, 97, 98, 98-2, 100, 101, 103, 109, 110, 111, 116, 117, 121, 129, 137, 137-1, 137-2, 139, 141, 144, 149, 150, 151, 152, 152-1, 919, 920, 921, 922, 923, 924, 925, 926, 941, 941-1, Guk-su Bong, Gates A, B, and C (97 buildings) • A periodical legal inspection → high-tension facilities
• Inspections of 6 special high-tension transformers on a request
• Replacements of CTs due to the remodeling of the building No.13
• Replacements of insulation oil(20 units at 14 buildings)
• An Integration of high-tension substations(137, 137-1 → 137-2)
• An Integration high-tension transformers and replacements of decrepit transformers at 6 buildings
• Self-repairs and inspections
The Second Power Plant Sunday, August 7th 08:00~12:00(4hr.) 18, 19, 25-1, 30, 30-1, 30-2, 31, 31-1, 32, 32-1, 33, 35, 37, 38, 39, 40, 41, 42, 42-1, 43-1, 44, 44-1, 45, 47, 48, 48-1, 69, 102, 104, 104-1, 104-2, 104-3, 105, 105-1, 107-1, 107-2, 107-3, 130, 131, 132, 133, 135, 138, 139-1, 142, 301, 302, 302-1, 310, 311, 312, 313, 314, 316, 330, 331, Jawoon-am, The Muniment Room (58 buildings) • A periodical legal inspection → high-tension facilities
• A replacement of 8,000KVA CT (400/5→500/5A)
• Safety checks of local substations (11 buildings)
• Replacements of insulation oil(20 units at 14 buildings)
• An Integration of high-tension transformers and replacements of decrepit transformers: at 8 buildings
• Self-repairs and inspections
The Third Power Plant Saturday, August 27th 07:00~13:00(6hr.) 49, 50, 51, 52, 52-1, 52-2, 53, 54, 55, 57, 57-1, 58, 59, 70, 74, 75, 75-1, 82, 99-1, 113, 140, 140-1, 200, 201, 203, 207, 220, 221, 222, 500, 506 (31 buildings) • An extension of the capacity (10,000→20,000kVA)
• Electrical safety works
• An Integration of high-tension transformers and replacements of decrepit transformers at 6 buildings
• Self-repairs and inspections
Saturday, August 27th 07:00~13:00(6hr.) 45, 48, 48-1, 104, 104-1, 104-3, 105, 105-1, 132 (9 buildings) • High-tension separating operation of Building No. 104

※ The date and time of the power outrage may be subject to minor changes.

3. Request for Cooperation:
  • A.For a proactive preparation, every related facility should let its members know of the exact date and time of the power outage.
  • B.Researchers should make proactive plans for experiment equipment which need to be powered all-time such as facilities for cultivation, freezing, and storage.
  • C.To prevent damages to electrical devices, please remove plugs from power outlets before the operation.
  • D.After power is resupplied, resume electricity use only after safety checks.
  • E.As security appliances such as CCTVs and other anticrime measures will stop operating during the power outage, please make separate anticrime plans.